Courthouse project update: steel structural assembly work completed
The latest update on construction of Union County’s new courthouse in Jonesboro was presented last Friday morning.
The update was shared at a regular meeting of the Union County Board of Commissioners. The meeting was at the community center in Jonesboro.
Friday’s report was drafted by courthouse construction project manager Mike Smith.
The report covered the period from April 20 through May 4. Highlights follow:
Grover Mays Construction completed the steel structural assembly. Welding continued on numerous types of braces throughout the structure. Cupola roof pans were being welded into place.
Tradesmen were installing heating, cooling, ventilating and exhaust ducts, as well as electrical and plumbing in the lower and first levels.
Charles Masonry continued to work in the lower level, which was complete for 95 percent of the rooms.
Bricks were being laid at the south, east and west elevations.
Level 2 detention cells at the courtrooms were 80 percent complete. Dispatch windows and doors were installed and grouted in, with work 9 percent complete.
Heartland Fire Protection was installing a sprinkler system in Level 1.
Boilers, a water heater, air handlers, a water pressure pump and plumbing were being installed at the lower level.
Roof and overflow cast iron drains were being piped through the building from the roof to the basement level to connect to the exterior storm drain on Mississippi Street.
Steel studs and exterior sheathing with water/vapor proofing were applied at Level 1 and Level 2 exteriors, with work by Miller Drywall 95 percent complete.
Interior steel studs had been set to 90 percent of the Level 1 rooms and 20 percent of the Level 2 rooms.
Lower level and stairwell steel stud walls began and were being laid out.
Roof top cooling unit anti-vibration units were set on their raised curbing by a crane. After the roofing is completed and flashed, then the cooling units will be lifted into position.
Roofers have installed roof sheathing, followed by a glue-down membrane.
Tapered foam insulation will be installed that will allow the final roof membrane to direct water runoff to 14 roof drains.
Then those drains will be run through to the lower level floor and out of the building and to the exterior storm drains on Mississippi Street.
Burkey Excavation has installed the building’s storm water drains.
The building’s septic line was extended and tapped into the Jonesboro sewage system.
Water services at Mississippi Street were being rerouted to allow for a 4-inch water main to be removed to make way for two, 20,000-gallon fire protection water tanks that will be buried adjacent to the new building.
The tanks are required by civil engineers and the Illinois State Fire Marshal’s codes to meet volume and pressure requirements to operate a fire suppression sprinkler system.