Courthouse project updated March 16
The latest update on the construction of Union County's new courthouse was shared Friday morning, March 16.
The update was presented at a regular meeting of the Union County Board of Commissioners. The meeting was March 16 at the community center in Jonesboro.
An update prepared by courthouse construction project manager Mike Smith showed the following highlights:
The level 1 slab-on grade area was poured March 9. This completed the level 1 floor.
Mays Construction completed assembly of the level 2 floor beams/floor pans and roof beams. Mays has "topped out" the cupola tower red iron. More welding will be done on "moment steel structures" and the cupola tower.
Cupola shop drawings have been received and the cupola cap was to be set on top of the current red iron. The cupola tower, with a three-foot spire, will be 67 feet above the first floor and 80 feet above the north parking lot.
Burkey Excavating completed installation of 30 percent of the storm drains that will be servicing the new courthouse and Mississippi Street in Jonesboro.
Final details were determined for doors, keying systems and hardware during a meeting on March 13 with River City Construction, the project manager and the supplier of locks and keying systems, Architectural Sales.
Union County Sheriff David Livesay and Capt. Scott Harvel met with River City to discuss and confirm the special keying systems for the detention area and the sheriff's offices.
Lower level services are being installed by the trades at the ceiling and I-beam level, including heating, cooling, ventilating and exhaust metal ductworks, as well as electrical and plumbing.
Masonry work in the lower level has been completed for 60 percent of the rooms. Rough-ins for plumbing and electrical work were being coordinated among the trades. Exterior masonry work at the lower level at the east, north and west continues.
The level 2 deck was scheduled to be poured in three sections last week, weather permitting.
Miller Drywall out of Missouri started March 7 with truckloads of steel studs and accessories, along with exterior sheathing. Steel stud walls were visible on the east, west and north elevations. Several window openings had been framed.
The west set of steel stairs serving all three levels had the tread pans filled with pea gravel concrete and troweled to receive a ceramic tile finish.
Detention grade cell door frames were scheduled to arrive on March 22.
Steel stud work was scheduled to start on level 2 this week.
The lower roof deck and the upper roof deck are to be set this week.
Block work at level 1 is scheduled to start this week.