Courthouse project's progress updated
The Union County Board of Commissioners received an update on construction of the county's new courthouse at the board's regular meeting Thursday morning, April 5, in Jonesboro.
A report for the period from March 16 to April 6 submitted by courthouse construction project manager Mike Smith follows:
As many as 45 workers and professional have been working daily for good progress and keeping the project on schedule for completion in April 2013.
Level 2 floor was poured on March 26-28. This completes L2 floor and brings the total concrete in the whole building at this time to 2,603 cubic yards which is more than 10 million pounds.
Mays Construction has completed the assembly of 95 percent of the steel structure. Welding on numerous types of braces throughout the structure continues.
Tradesmen are installing heating, cooling, ventilating and exhaust metal ductwork as well as electrical and plumbing in the lower level.
Masonry work in the lower level is completed for 75 percent of the rooms.
Exterior masonry at the lower level on the east, north and west are complete.
Brick work was scheduled to start at the south and east elevations during the week of April 9. The first of the 95,000 brick ordered for the exterior finish has arrived.
Dispatch windows and doors are being installed and grouted in.
Stiles Office Supply of Carbondale took the bid on the dispatch console furniture and its installation in the sheriff's department.
Heartland Fire Protection has begun installing the sprinkler system in Level 1.
Boilers, water heater, air handlers, water pressure pump, HVAC ducts and plumbing are being installed at the lower level.
Steel studs and exterior sheathing with water/vapor proofing applied at Level 1 exterior is 85 percent complete by Miller Drywall.
Installation of 8-inch steel studs and accessories has begun at exterior walls of Level 2.
Detention grade cell door frames are on site and several have been installed and grouted into position.
Lower roof deck has been installed and is ready for roofing. Upper roof decking was scheduled to be placed during the week of April 9 and roofing was planned for April 2-6.