Latest courthouse project update shared

Permanent power has been installed to Union County's new courthouse.

An update on the courthouse construction project was shared at last Friday morning's regular meeting of the Union County Board of Commissioners.

The meeting was at the community center in Jonesboro.

Courthouse construction project manager Mike Smith presented a report which highlighted progress made from July 6 through July 20.

Along with permanent power being installed to the building, other highlights included:

Subpanels were being wired from the electric room.

Installation of elevators was scheduled to start July 23. Installation is expected to take about 40 working days to complete.

The east tower wall and south wall of the main building were being bricked. The west wall and part of the south wall stone cap were installed last week with the assistance of a large crane.

Interior steel studs are 100 percent complete at the lower level, 100 percent complete on Level 1 and 75 percent complete on Level 2.

Lower level drywall has primer and two coats of finished paint. The work will be inspected for deficiencies before the final coat is applied. Taping of drywall on Level 1 has begun.

Installation of detention doors and hardware was scheduled Monday, July 23.

Work continued on installation of heating, cooling, ventilating and exhaust ducts, as well as electrical and plumbing at all levels. The lower level was 90 percent complete, with the exception of the mechanical room. Level 1 was 90 percent complete. Level 2 was 75 percent complete.

The cupola's exterior metal wall system has been completed and was ready for glaziers to intall the window frames and glass panes. Roofers completed tower roofing. The cupola cap is scheduled for delivery during the first week of August.

Aluminum window frames and insulated glass have been delivered and will be installed in coming weeks. Other elevation openings will not be filled until the brick and stone are completed and cleaned. That work was scheduled to begin this week.

A sample of the courtroom pew has arrived. The sample has been "tested" and approved for production.

Fire pumps are slated for delivery during the last week of July/first week of August.

Fire stopping, to meet Illinois Fire Code guidelines, is being carried out at the lower level.

The projected timelines still call for the sheriff's office and 911 to move into the lower level of the new building in October.

Demolition of the old sheriff's office and four neighboring houses will follow the move.

Old courthouse offices are scheduled to move into the new building starting on Jan. 1, 2013.

Demolition of the old courthouse is scheduled to begin in February 2013.


        Archive Section: 

        The Gazette-Democrat

        112 Lafayette St.
        Anna, Illinois 62906
        Office Number: (618) 833-2158
        Email: news@annanews.com

        Sign Up For Breaking News

        Stay informed on our latest news!