Major progress for courthouse project
Major progress can be seen at the construction site of a new Union County courthouse building in Jonesboro.
A progress report was shared at last Friday morning's regular meeting of the Union County Board of Commissioners.
The meeting was at the community center in Jonesboro.
Courthouse project construction manager Mike Smith reported on the following progress since Feb. 3:
The lower level exterior wall was completed by a concrete pour on Feb. 12.
Mays Construction received eight more semi loads of steel and started assembly of level 2 floor beams/floor pans and the cupola tower.
Steel sequence number 3 for additional steel semi loads were due Feb. 21-22.
Footings to the south of the basement wall will continue to be excavated and poured as weather allows.
Gravel backfill at the slab-on grade area on the south wall continues.
As of Feb. 17, 2,297 cubic yards of concrete had been poured.
152 of a total of 258 door frames were delivered.
Details for communi-cations, camera, recording, security systems, data and phone have been specified.
Final details are being determined for doors and hardware.
Forming and pouring of the wall/column line at the south wall of level 1 continues.
Masonry work in the lower level has begun for several rooms. Rough-ins for plumbing and electrical services are being coordinated among the tradesmen and with the Ron Charles masons.
Lower level above grade services are being installed by the trades at the ceiling beam level.
The radio tower and dispatch consoles and dispatch furniture have been put out for bid.
Smith also reported that in the near future:
Exterior masonry at the lower level at the east, north and west will begin.
More of the steel skeleton will take shape.
The dispatch furniture will go out for bid.
A second deck pour is planned during the first part of March.
Miller Drywall will begin steel stud installation on level 1 in the next two weeks.
Shop drawings for the cupola's fabrication are due in March.