Move into new courthouse planned

If all goes as planned, and everything appears to be moving ahead on schedule, two offices are scheduled to move into Union County's new courthouse next week.

An update on the courthouse construction project was given at a regular meeting of the Union County Board of Commissioners which was held last Friday morning. The meeting was at the community center in Jonesboro.

The update was presented by courthouse construction project manager Mike Smith. He noted that Sept. 21 was the 252nd day of construction on the new courthouse.

The most current timeline projects that the Union County Sheriff's Office and Union County 911 will move into the new facility on Monday, Oct. 1.

Other offices are scheduled to begin moving on Jan. 1, 2013.

The two offices will be located in the lower level of the new courthouse. The new facility is being built directly behind the existing structure.

Highlights in the progress report follow:

The new west parking lot has been paved and sidewalks have been poured.

The west parking lot was scheduled to be striped on Friday, Sept. 21, and opened Monday, Sept. 24, with 22 staff parking places.

The north parking lot was scheduled to be marked Sept. 21, which would create 21 additional parking spaces.

Installation of two of the three elevators in the building was nearly complete. Final details were to be completed on the third elevator. An inspection by the State of Illinois will follow installation of the elevators before they are put into use.

Installation of steel studs was complete at all levels. More than 92,000 pounds of studs have been used in construction of the courthouse.

The courthouse interior walls have been covered with 173,600 square feet of drywall, or 3,600 pieces of 4-foot by 12-foot 5/8 sheets.

Furniture was installed for 911 dispatch. Consoles were being programmed.

Heating, cooling, ventilating and exhaust ducts, electrical and plumbing installation were complete. The system has been tested and is running in the lower level.

Two gas boilers have been tested. They have a total output capacity of 1.6 million BTUs per hour to heat the whole building. Each room in the courthouse will have its own thermostat.

Jonesboro city water has been turned on.

Light fixtures were being installed in the lower level and in 911 dispatch. Smoke and fire detectors were installed in the lower level.

Hundreds of boxes of records have been moved from the existing courthouse into the lower levels of the new building.

Demolition of two wood-framed houses on the grounds is scheduled to begin Thursday, today.


        Archive Section: 

        The Gazette-Democrat

        112 Lafayette St.
        Anna, Illinois 62906
        Office Number: (618) 833-2158
        Email: news@annanews.com

        Sign Up For Breaking News

        Stay informed on our latest news!